January 4, 2011 Board Meeting
Agenda Item #33


Title
APPROVAL OF CONTRACT FOR CONSTRUCTION FOR THE BOOKER HIGH SCHOOL REBUILD PROJECT: PHASE II - DEMOLITION & SITEWORK - UTILITY RELOCATION

Description

Under the terms of the 11/17/2009 (Item#30) Board approved "CONSTRUCTION MANAGER'S PRECONSTRUCTION SERVICES CONTRACT FOR THE BOOKER HIGH SCHOOL - REBUILD PROJECT", the Director of Construction Services and a member of the Professional Services Selection Committee (PSSC) have successfully negotiated a contract with Willis A. Smith, Inc. for a portion of the Booker High School Rebuild Project.  The 11/17/2009 agreement included pre-construction and bidding services only.  The scope of this contract shall include construction management services necessary to complete demolition, site development, and utility relocation for the Booker High School Rebuild Demolition and Site Work Phase according to DMK Associates and Harvard Jolly Architects plans dated November 12, 2010.  The Guaranteed Maximum Price (GMP) of this contract is $5,042,533.00.  The remaining contracts for construction will be negotiated upon completion of those Contract Documents.  This contract is available for review at the Construction Services Department.  The School Board attorney has approved the use of this contract.  Funds for this contract are available in the project budget account.



Recommendation
That the Contract for Construction for the Booker High School Rebuild Project:  Phase II - Demolition & Sitework - Utility Relocation be approved as presented.

Contact
LEMPE & DOUGHERTY

Financial Impact
$5,042,533.00 - Capital